How a New Zealand Water Treatment Facility Avoided the Pitfalls of Data Sludge

Data Sludge

“Just because something works doesn’t mean it can’t be improved.” This is a line from Marvel’s Black Panther that Daniel Jones, Information Management Lead at GHD, quoted during a recent Autodesk University session, “From Data Sludge to Liquid Gold.” For Jones, this quote perfectly reflects the opportunities a digitally transformed, ‘shift left’ approach to data handovers can provide to construction project workflows.

During the session, Jones explored how his team at GHD abandoned status quo information management frameworks and adopted a ‘shift left’ data strategy throughout a recent future-proofing, upgrade project for Wellington Water’s Te Mārua Road Water Treatment Plant in Wellington, New Zealand, which resulted in hundreds of thousands of dollars in savings for the facility.

Prioritizing Project Data on Day 1

The Te Mārua project is a critical $100 million (NZD) upgrade to one of New Zealand’s largest water treatment facilities that provides drinking water to nearly half of the Wellington region’s population. The future-proofing, upgrade project is the plant’s most significant upgrade since 1980 and increases Te Mārua’s output capacity from 80 million liters to 140 million liters a day.

According to Jones, a major upgrade like Te Mārua is accompanied by significant challenges, including the fact that 80 percent of a project’s total lifecycle cost is in the operation and maintenance phases. This operational challenge is made even more difficult since the handover data needed to run a facility like Te Mārua is often unusable.

“In the past, this has meant Wellington Water faced delays of 12 to 18 months just for manual data processing and verification before information could be entered into their asset management system,” Jones said. “We call this problem data sludge. On this project, we made it our mission to solve it for Wellington Water, ensuring the long-term value of their investment was protected right from the start.”

“[As a result], at the end of the construction phase a huge amount of valuable information is lost during the project handover. This is a reactive approach, where we are always trying to fix problems when they are most expensive. We are essentially set up to fail.” –Daniel Jones

Jones explained that his team’s ability to influence project outcomes was at its highest at the beginning of the upgrade project, when the cost of making changes was at its lowest. Unfortunately, traditional project workflows force teams to solve data sludge problems at the end of the project, just before the operations phase.

“[As a result], at the end of the construction phase a huge amount of valuable information is lost during the project handover,” Jones said. “This is a reactive approach, where we are always trying to fix problems when they are most expensive. We are essentially set up to fail.”

To avoid the data sludge pitfalls that traditional project workflows face, Jones and his team adopted a ‘shift left’ strategy and invested their effort in defining information requirements at the start of the project when their influence was at its height. “This approach allows us to…build the amount and value of our information collaboratively,” Jones said. “This was about treating information as a critical asset from day one, not as an afterthought.”

‘Shifting Left’: The New Data Lifecycle of a Project Asset

To demonstrate how a ‘shift left’ strategy was leveraged during the Te Mārua project, Jones presented the journey of a single project asset throughout its entire digital lifecycle: a small flow control valve named FCV 5501. Jones walked his audience through FCV 5501’s digital conception, development on the construction site, and into its adult life in operations.

Jones explained that the ‘shift left’ approach to the project data began with a single question: what information will Wellington Water need to run this plant for the next 30 years? “Many of the answers came directly from their existing Maximo operational system,” Jones said. “This led us to define a comprehensive data scheme of 312 attributes for every asset class, all structured in a simple Excel matrix, ensuring that these hundreds of operational requirements would be accurately and consistently captured by designers without creating a massive, complex, and hated administrative burden.”

“We identified that 80 percent of this data could be delivered during the design phase, not at handover, even if it was preliminary and subject to change during construction.” –Daniel Jones

Manually creating 312 parameters within Wellington Water’s Autodesk tools would ultimately be a slow, torturous process, Jones said. “So we automated it. We configured Dynamo scripts and SQL queries that read the Excel file and automatically configured the design models in Revit, Civil 3D, and Plant 3D. These steps reduced the technical setup time from days to just a few minutes. But more importantly, it guaranteed 100 percent consistency and compliance with Wellington Water’s data standards and exchange information requirements.”

It was at this point in the project that Jones and his team came to a breakthrough realization. “We identified that 80 percent of this data could be delivered during the design phase, not at handover, even if it was preliminary and subject to change during construction,” Jones said. “It meant that for the data that wasn’t going to change, Wellington Water had it in their systems before the physical asset was built. This fundamentally shifted the responsibility of data quality upstream. This is the very essence of the ‘shift left’ principle in action, moving their effort earlier in the project to ride the wave of increasing value rather than fighting against it in the end.”

According to Jones, the automation his team orchestrated during the project was a game changer, enabling design teams to focus on higher-priority tasks. “It freed our design teams to focus on what they do best: designing,” Jones said. “And the big win was a high-quality design project information model (PIM). This PIM was a fully compliant design stage asset register, complete with drawings, documents, and of course the 3D geometry. The value became immediately clear. Wellington Water could start creating assets in their Maximo system a full 12 months earlier than usual.”

“This handover point is where the relay baton of information is usually dropped. To avoid that, we built a fully digital collaborative workflow, integrating our Autodesk CDE with an Esri ArcGIS platform. This created a seamless bridge in our common data environment, connecting designers, contractors, and the owner – in real-time.” –Daniel Jones

“We collaboratively prioritized a core set of the most critical attributes for handover,” he said. “And because of our automated setup, the full detailed data schema was still embedded in the models. This means that the models are future-proofed and ready for more detailed information as Wellington Water’s data strategies evolve. With its digital DNA now defined, FCV 5501 was ready to move from the controlled environment of design to the dynamic reality of construction. FCV 5501 is now a data-rich digital entity.”

At this point in the process, Jones and his team had a high-quality design PIM that needed to get into the hands of the construction team. “This handover point is where the relay baton of information is usually dropped,” he said. “To avoid that, we built a fully digital collaborative workflow, integrating our Autodesk CDE with an Esri ArcGIS platform. This created a seamless bridge in our common data environment, connecting designers, contractors, and the owner – in real-time.”

Digitally Transforming As-Built Information Capture

The next step in the plant upgrade journey was for Jones and his team to provide the project’s lead contractor with a simple and efficient way to capture as-built information.

“Traditional paper forms are slow and lead to errors, so we empowered the field teams to become guardians of data quality,” said Jones. “We used Survey123 forms, but with a critical innovation. They were prepopulated with data directly from the design PIM. This meant that field teams weren’t creating data from scratch. They were simply validating and enriching it. We designed the process to be incredibly efficient.”

“This process guarantees that the documentation, 3D models, and the asset data are all perfectly aligned. We have a smooth, controlled flow of value. The ultimate intent is that this accepted information can now seamlessly integrate with Wellington Water’s existing systems. This provided the foundation for an operational digital twin.” –Daniel Jones

Jones then returned to FCV 5501’s story. At this point, the valve had been physically installed, but the work was not over. “How do we ensure that the incredible digital value we’ve created provides a return on investment for the next 30 years?” Jones asked. “We closed the loop. The final, validated as-built data was pushed back into the master BIM models. These models were then integrated with ArcGIS using GeoBIM to create the proof of concept for a true operational digital twin.”

Since Jones’s team avoided the typical data dump that occurs at the end of a project, the client had already accepted a verified set of complete, as-built information once the facility upgrade was completed.

“The emphasis here is on synchronization and consistency,” said Jones. “This process guarantees that the documentation, 3D models, and the asset data are all perfectly aligned. We have a smooth, controlled flow of value. The ultimate intent is that this accepted information can now seamlessly integrate with Wellington Water’s existing systems. This provided the foundation for an operational digital twin.”

The Tangible Benefits of ‘Shifting Left’

According to Jones, when all of this facility data is pulled together, owners and operators can build a digital history of each asset that is organized, retrievable, and usable across time and projects. “This isn’t just a model, it’s an operational tool,” said Jones. “It gives operators a real-time, reliable window into their assets. It puts the right information in the right hands at the right time. This is how we turn data sludge into liquid gold, and that outcome is only possible because we committed to a structured, data-driven process from day one.”

In the end, the digital transformation that Jones and his team implemented to Wellington Water’s project workflows enabled them to deliver the complete asset register a full 12 months ahead of a traditional schedule.

“This acceleration resulted in an estimated $370,000 in savings and freed up approximately 3,300 hours of our team’s time that would have been spent on manual data management,” Jones reported. “Most importantly, we had almost entirely eliminated the data processing backlog at handover. The information was clean, structured, and loaded directly into Wellington Water’s Maximo system.”

To watch this Autodesk University session in full, click HERE.

Tags

Related Posts
Data management

How Better Data Management Can Reduce Government Project Delays and Cost Overruns

Billions of dollars over budget. Years behind schedule. Thousands of changes along the way. For government agencies responsible for massive infrastructure projects, these outcomes aren’t ...
Read More →
Nature-based solutions

How Nature-Based Solutions Are Reshaping Infrastructure Design

The future of resilient infrastructure may depend as much on working with nature as it does on engineering around it. Traditionally, engineers have relied heavily ...
Read More →
Stowe Australia

Stowe Australia Shares 3 Lessons for Preparing Construction Data for AI

The use of Artificial intelligence (AI) across the architecture, engineering, and construction (AEC) industries is skyrocketing, with organizations eager to embrace agents, predictive analytics, and ...
Read More →